Project templates/Audit

401(k) plan audit

Recurs yearly · 1 open project follows it

TaskPhaseGoes toDueEstimateMilestone
Acceptance and continuancePlanningSenior managerDay 2
Independence confirmationPlanningSenior managerDay 5
Risk identification meetingPlanningSenior managerDay 8
Participant data testingFieldworkSeniorDay 26
ContributionsFieldworkSeniorDay 27
DistributionsFieldworkSeniorDay 28
Investments and fair valueFieldworkSeniorDay 29
Notes to the financial statementsFieldworkSeniorDay 30
Subsequent events reviewWrap-upSenior managerDay 34
Management representation letterWrap-upSenior managerDay 36
Form 5500 filing packageProcessingAdministrationDay 44

A task after another has no date until that task is done. A task goes to the person who holds its role on the project, or to whoever holds its phase. The estimate is shown to administrators only and does not change the budget.